Show all «Technical follow-up»
Action | Tech. Officer | Contractor | |
---|---|---|---|
Reception of a work request from a CERN customer. |
|||
Request a quotation in compliance with contract terms and deadlines. |
|||
Review the bid (unit prices in accordance with the contract, proposed quantities of material, proposed duration of the works etc.) – iterate with the contractor as necessary to come to an acceptable bid. |
|||
In case of use of GESMAR, upon acceptance of the bid, create the order in GESMAR, and submit it to the contractor. In case GESMAR is not used, please refer to section “financial commitments”. |
|||
Where applicable, two weeks before the start of work, create an “IMPACT” request for any new work to be performed (formerly called “avis d’ouverture de chantier”). In case the technical officer needs further information on how to use IMPACT, there is a course “IMPACT Fundamentals" available at https://sir.cern.ch . This course, in English or French, covers the basics for IMPACT. |
|||
Should a "Visite d’Inspection Commune" (VIC) be necessary, the related VIC form should be completed in IMPACT. For further details on VIC, please refer to section “Follow-up of contract implementation – Visite d’inspection commune”. |
|||
Performance of the work. |
|||
If needed, follow-up closely the execution of the work, with the presence of CERN’s technical responsible(s) and/or the technical officer.
|
|||
Raise “Point d’Alerte” (PAL) for any deviation to the planned work.
|
|||
Perform the acceptance test on site, with presence or supervision of CERN’s representatives. It is sometimes impossible to verify all the interventions performed. In such case, the technical officer shall perform sample verifications. |
|||
For EN-EL only: once the work is completed, submit the bill of quantity (“métré”) of the work performed. |
|||
For EN-EL only: Verify the bill of material, performing a contradictive bill of material (“contre-métré”) , with on site visit when necessary. |
|||
For EN-EL only: Update of the bill of quantity in GESMAR (only if duly justified against actual work). |
|||
Follow up Key Performance Indicators (KPIs), as defined in the contract.
|
Action | Tech. Officer | Contractor | |
---|---|---|---|
Where applicable, open a Work Order / Ordre de Maintenance (ODM) to instruct the start of a new intervention. |
|||
Perform the intervention and verify compliance of the work, in accordance with the maintenance plan - as foreseen in Infor EAM / ODM, and agreed with the technical officer.
|
|||
Verify the interventions performed, based on sample checks, or systematic, as appropriate. Re-open the work order as appropriate if the work performed is not compliant (via Infor EAM where applicable).
|
|||
Validation of the work performed (via Infor EAM where applicable).
|
|||
Follow up Key Performance Indicators (KPIs), as defined in the contract.
|
Action | Tech. Officer | Contractor | |
---|---|---|---|
Request for an intervention in compliance with contract terms and deadlines. |
|||
Perform the intervention. |
|||
Notify CERN’s technical responsible, in writing, of completion of intervention (via Infor EAM where applicable). |
|||
Systematic or sample verification of the work performed, as appropriate. Re-open the work order / ODM when the work performed is not compliant. |
|||
Validation of the work order / ODM. |
Action | Tech. Officer | Contractor | |
---|---|---|---|
Perform the work, deliver the service according to the deadlines and content agreed.
|
|||
Check the work performed. Validate it or submit comments, as appropriate.
|
|||
Analyse users’ complaints, as the case may be. |
|||
Treat users’ complaints, as the case may be. |
|||
In case of time-spent remuneration, declare the number of hours / days performed during the month.
|
|||
Validation of number of hours of work performed by the contractor, authorizing the invoice to be issued.
|
|||
Follow up Key Performance Indicators (KPIs), as defined in the contract.
|
Action | Tech. Officer | Contractor | |
---|---|---|---|
Submit KPIs and / or SLA report in accordance with the Quality Assurance Plan defined in the technical specifications.
|
|||
Evaluate the contractor’s performance via CERN’s own system/tools, measuring CERN’s monthly KPIs and SLA and in accordance with the Quality Assurance Plan defined in the technical specifications and the Quality Assurance Plan.
|
|||
Review KPIs / SLA during contractual follow-up meetings (monthly or quarterly). |
|||
Apply penalties as the case may be, deducting the related amount from invoices in accordance with the periodicity defined in the contract (monthly usually).
|
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Document every NC (for example with pictures, “Ordre de Service” (OS)) at least on a monthly basis.
|
||||
Inform the contractor about the Non-conformities via an “Ordre de Service” (OS) - requesting management of non-conformities in accordance with the contractual documents (contract, technical specification, evaluation questionnaire, Quality Assurance Plan etc.) - (See section “Correspondence” for further details), with procurement service in copy if related to commercial or contractual issues. |
||||
Apply penalties as the case may be.
|
||||
Take remedial measures / corrective actions. |
||||
Check the result and efficiency of remedial measures / corrective actions. |