Show all «Contract execution»
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Check that all actions agreed as part of the contract and meetings of the implementation phase are actually implemented (number and qualification of resources, organization chart, deadlines, registration and access rights, follow-up of the services already performed, etc.). |
||||
If applicable, retrieve an inventory of CERN’s assets, special tools and spares from CERN’s database (Infor EAM etc.) and submit it to the contractor. |
||||
If applicable, verify and establish an inventory of CERN’s assets, special tools and spares available in CERN’s stores and return it to the technical officer within the deadlines set forth in the contract. |
||||
Verify – comparing proposed inventory against information available (in Infor EAM where applicable) - and modify the quantities in Infor EAM, as appropriate.
|
||||
Validate and/or sign the assets and spare parts inventory. |
||||
Collect and accept or approve all deliverables (template of monthly/quarterly reports, Quality Assurance Plan (QAP) etc.) due, within the conditions and deadlines set forth in the contract.
|
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Hold weekly operational meetings, as appropriate.
|
||||
Send the agenda and invitation to weekly operational meetings. The agenda shall include all aspects related to operational issues, including Safety, schedule of activities etc. Participants shall include at least:
|
||||
Draft and issue the minutes of the operational progress meeting – preferably via a Service Order / Ordre de Service (OS).
|
||||
File the minutes of the weekly progress meeting in EDMS. |
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Send contractual meeting invitations with agenda. The contractual meetings should be held on a regular basis (monthly, quarterly, yearly), in accordance with the conditions defined in the contract. Participants shall include at least:
The agenda of the contractual meetings shall include all aspects related to administrative, technical and financial follow up, as described in the section below.
|
||||
Hold preparatory meetings, covering technical, commercial and contractual matters, as appropriate. |
||||
Hold the contractual meetings, following the agenda previously communicated, in particular:
|
||||
Draft the minutes of contractual meetings, send it for review to the procurement officer.
|
||||
Sign and communicate / notify the minutes of contractual meetings to the contractor. |
||||
Sign the minutes of contractual meetings and submit it to the technical officer. |
||||
File the minutes of progress meeting (both in paper and electronic format). Technical and procurement officers shall use their own data management system. |
Action | Tech. Officer | Contractor | |
---|---|---|---|
Reception of a work request from a CERN customer. |
|||
Request a quotation in compliance with contract terms and deadlines. |
|||
Review the bid (unit prices in accordance with the contract, proposed quantities of material, proposed duration of the works etc.) – iterate with the contractor as necessary to come to an acceptable bid. |
|||
In case of use of GESMAR, upon acceptance of the bid, create the order in GESMAR, and submit it to the contractor. In case GESMAR is not used, please refer to section “financial commitments”. |
|||
Where applicable, two weeks before the start of work, create an “IMPACT” request for any new work to be performed (formerly called “avis d’ouverture de chantier”). In case the technical officer needs further information on how to use IMPACT, there is a course “IMPACT Fundamentals" available at https://sir.cern.ch . This course, in English or French, covers the basics for IMPACT. |
|||
Should a "Visite d’Inspection Commune" (VIC) be necessary, the related VIC form should be completed in IMPACT. For further details on VIC, please refer to section “Follow-up of contract implementation – Visite d’inspection commune”. |
|||
Performance of the work. |
|||
If needed, follow-up closely the execution of the work, with the presence of CERN’s technical responsible(s) and/or the technical officer.
|
|||
Raise “Point d’Alerte” (PAL) for any deviation to the planned work.
|
|||
Perform the acceptance test on site, with presence or supervision of CERN’s representatives. It is sometimes impossible to verify all the interventions performed. In such case, the technical officer shall perform sample verifications. |
|||
For EN-EL only: once the work is completed, submit the bill of quantity (“métré”) of the work performed. |
|||
For EN-EL only: Verify the bill of material, performing a contradictive bill of material (“contre-métré”) , with on site visit when necessary. |
|||
For EN-EL only: Update of the bill of quantity in GESMAR (only if duly justified against actual work). |
|||
Follow up Key Performance Indicators (KPIs), as defined in the contract.
|
Action | Tech. Officer | Contractor | |
---|---|---|---|
Where applicable, open a Work Order / Ordre de Maintenance (ODM) to instruct the start of a new intervention. |
|||
Perform the intervention and verify compliance of the work, in accordance with the maintenance plan - as foreseen in Infor EAM / ODM, and agreed with the technical officer.
|
|||
Verify the interventions performed, based on sample checks, or systematic, as appropriate. Re-open the work order as appropriate if the work performed is not compliant (via Infor EAM where applicable).
|
|||
Validation of the work performed (via Infor EAM where applicable).
|
|||
Follow up Key Performance Indicators (KPIs), as defined in the contract.
|
Action | Tech. Officer | Contractor | |
---|---|---|---|
Request for an intervention in compliance with contract terms and deadlines. |
|||
Perform the intervention. |
|||
Notify CERN’s technical responsible, in writing, of completion of intervention (via Infor EAM where applicable). |
|||
Systematic or sample verification of the work performed, as appropriate. Re-open the work order / ODM when the work performed is not compliant. |
|||
Validation of the work order / ODM. |
Action | Tech. Officer | Contractor | |
---|---|---|---|
Perform the work, deliver the service according to the deadlines and content agreed.
|
|||
Check the work performed. Validate it or submit comments, as appropriate.
|
|||
Analyse users’ complaints, as the case may be. |
|||
Treat users’ complaints, as the case may be. |
|||
In case of time-spent remuneration, declare the number of hours / days performed during the month.
|
|||
Validation of number of hours of work performed by the contractor, authorizing the invoice to be issued.
|
|||
Follow up Key Performance Indicators (KPIs), as defined in the contract.
|
Action | Tech. Officer | Contractor | |
---|---|---|---|
Submit KPIs and / or SLA report in accordance with the Quality Assurance Plan defined in the technical specifications.
|
|||
Evaluate the contractor’s performance via CERN’s own system/tools, measuring CERN’s monthly KPIs and SLA and in accordance with the Quality Assurance Plan defined in the technical specifications and the Quality Assurance Plan.
|
|||
Review KPIs / SLA during contractual follow-up meetings (monthly or quarterly). |
|||
Apply penalties as the case may be, deducting the related amount from invoices in accordance with the periodicity defined in the contract (monthly usually).
|
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Document every NC (for example with pictures, “Ordre de Service” (OS)) at least on a monthly basis.
|
||||
Inform the contractor about the Non-conformities via an “Ordre de Service” (OS) - requesting management of non-conformities in accordance with the contractual documents (contract, technical specification, evaluation questionnaire, Quality Assurance Plan etc.) - (See section “Correspondence” for further details), with procurement service in copy if related to commercial or contractual issues. |
||||
Apply penalties as the case may be.
|
||||
Take remedial measures / corrective actions. |
||||
Check the result and efficiency of remedial measures / corrective actions. |
Action | Tech. Officer | Contractor | |
---|---|---|---|
Use Service Order / Ordre de Services (OS) for every communication concerning contractual obligations, defining clearly CERN’s instructions, inventories, identified non-conformities, requested deadlines etc.
|
|||
Countersign the OS and submit the document, including answers as requested to the technical officer within within the deadline for answer requested in the OS.
|
Action | Tech. Officer | Contractor | |
---|---|---|---|
Manage accesses and authorisations in compliance with CERN access and registration procedures.
|
|||
At least once a year, follow-up the contractor’s personnel renewal of registration and access authorisations (in accordance the document “Working on the CERN site”):
|
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Declare any subcontractor to CERN for approval. The request shall be made in writing, and shall include:
|
||||
Check contractual conditions (subcontracting allowed (Y/N), maximum percentage and type of activities allowed), accept the firm or not and submit the contractor’s request of subcontractor registration including name and address to the procurement officer for approval. |
||||
Verify contractual conditions, and confirm whether the subcontractor is blacklisted or not. |
||||
Approve or reject the request and send a confirmation to the contractor. In case of confirmation, the letter shall request the contractor to proceed with all administrative measures (access, authorisations etc.) necessary for the performance of the services by the subcontractor (see section “Registration and access of the contractor’s personnel”). |
||||
Update the Prevention Plan (PP) with the subocntractor name to be listed as part of subcontractors declared under the contract. |
Action | Tech. Officer | Contractor | |
---|---|---|---|
In case of work outside of CERN normal working hours (from 19h00 to 7h00 or during week-ends or bank holidays), where applicable, ask French (DIRECCTE) or Swiss (OCIRT, SECO) authorities, as applicable, authorization to work outside normal working hours.
|
|||
Submit for approval "work notification" / "avis d’exécution de travaux en dehors de la plage horaire admise comme horaire normal" five working days at the latest before the start of work.
|
|||
Approve (and sign) or reject "work notification" / "avis d’exécution de travaux en dehors de la plage horaire admise comme horaire normal". |
|||
When approved, submit the signed "work notification" / "avis d’exécution de travaux en dehors de la plage horaire admise comme horaire normal" to CERN security services with the technical officer and CERN Fire and Rescue service in copy, at the latest 48 hours before the intervention. |
Action | Tech. Officer | Contractor | |
---|---|---|---|
Iterate regularly (in particular during follow-up meetings) with the contractor about:
|
|||
Submit regularly (at least once a year) the list of contractor’s and subcontractor’s personnel and the list of subcontractors assigned to the contract. |
|||
Check regularly (at least once a year) the contractor’s personnel list and list of subcontractors, in accordance with the list of the contractor’s personnel in HRT and according to section “Registration and access authorizations”. |
|||
Document all Safety discussions –including when no issue is escalated- in the minutes of meetings. |
|||
Update the PP, as appropriate (see section below).
|
Action | Tech. Officer | Contractor | |
---|---|---|---|
Update the PP as often as needed, based on issues raised during periodical follow-up meetings. The PP shall be updated at least once per year.
|
|||
Update the PP and re-submit it, as appropriate. |
|||
Sign the updated PP. |
|||
File the updated PP in EDMS. |
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Declare accidents, incidents and near misses using A2 form, in EDH. Inform both the technical and procurement officers.
|
||||
Review declaration, iterate with HSE Unit and the contractor. Submit CERN comments to the contractor, as necessary.
|
||||
Modify A2 form as needed |
||||
If requested by HSE Unit, contribute to the Safety investigation. |
||||
Update the PP, should this be necessary on the basis of conclusions of the Safety investigation. |
Action | Tech. Officer | Contractor | |
---|---|---|---|
For work contracts, upon creation of an “IMPACT” request form, should the technical officer consider that a “Visite d’Inspection Commune” (VICs) is necessary, perform the “Visite d’Inspection Commune” (“VIC”). The VIC shall involve at least:
|
|||
Draft the report of VIC in “IMPACT” (refer to the VIC section available in the “IMPACT” form). Submit it to the contractor. |
|||
Sign the report of VIC. |
Action | Tech. Officer | |
---|---|---|
Request budget to the « Department Planification Officer » (DPO) or customer’s DPO, with a description of services needed and that are proposed to be performed. In particular for work contracts (type C): request budget code to customer. |
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Request a quotation for the performance of services under the contract when the budget allocated is confirmed by the DPO. |
||||
Review of quotation submitted by the contractor (in particular for small works contracts). |
||||
Creation of the « Ordre de Service Valant Commande » (OSVC) via EDH..
|
||||
Creation and issuing of the order (OV) to the contractor. |
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Order services under the contract when the budget allocated to the contract is confirmed by the DPO. |
||||
Review of quotation submitted by the contractor (in particular for C contracts), on the basis of the conditions defined in the contract. |
||||
Creation of OSVC via GESMAR. |
||||
Creation and issuing of OV to the contractor. |
Action | Proc. Officer | Tech. Officer | |
---|---|---|---|
Provide IPT department (Stéphanie Blanchard) with estimates of yearly expenses under the contract. Prepare justification in case the estimated annual expenses are expected to exceed the amount authorised by the Finance Committee. Decide whether the contract should be renewed or not.
|
|||
Submit to Finance Committee (FC) the annual report on industrial service contracts, including requests for contract renewal, estimated yearly expenses and justification for contracts for which authorised amounts are expected to be exceeded. |
|||
During the ongoing financial year, inform the procurement officer when FC’s authorized amount is about be exceeded. Provide justification in case additional amounts are to be resubmitted to FC for approval. |
Action | Proc. Officer | Tech. Officer | |
---|---|---|---|
Forward invoices to accounts-payable@cern.ch if received by mistake. |
|||
Verify invoices received from accounts payable on the basis of conditions defined in the contract / OV (order). |
|||
Approve or reject discrepancies identified in invoices by accounts payable via EDH. Sign and date invoice if compliant. Submit signed and dated invoice to accounts payable (accounts-payable@cern.ch), with appropriate supporting document – as necessary. In case of rejection, provide appropriate justification to accounts payable.
|
Action | Tech. Officer | |
---|---|---|
Refuse the proposed prices and request the strict application of contractual prices.
|
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Forward any request of revision of prices to the procurement officer. |
||||
In case price revision request does not comply with the contract provision on price revision, refuse the proposed revision and request the strict application of contractual prices. In case revision of prices complies with contract provision on price revision and provided the procurement officer agrees with the request, prepare a contract amendment (see section on amendments for further details).
|
Action | Tech. Officer | |
---|---|---|
Do not approve any acceptance document of the work performed - including as part of minutes of meetings or by email. |
||
Raise reserves –preferably via a Service Order / Ordre de Service (OS) - as soon as any non-conformity identified, asking for a corrective plan and fixing deadlines. |
||
Retain payment of the corresponding invoices, notifying accounts payable (accounts-payable@cern.ch), until the remedy of non-compliance. |
Action | Tech. Officer | Contractor | |
---|---|---|---|
Retain payment of the invoice immediately.
|
|||
Inform the contractor. Ask the contractor to issue a correct invoice, as necessary.
|
|||
Apply penalties as appropriate. |
Action | Tech. Officer | |
---|---|---|
Refuse any deviation to the contract provisions.
|
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Check the contractor's proposed press release from a technical point of view and forward the contractor's request to IPT department (Sébastien Sonnerat, with the procurement officer in copy) and IR department (Fabienne Landua) .
|
||||
Approve or reject contactor’s request, in collaboration with the logo committee. |
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Inform the procurement officer as soon as possible.
|
||||
Assess the situation:
|
||||
Hold meeting(s) with the contractor, as appropriate.
|
||||
Prepare letter of notice ensuring that it:
|
||||
Send the notice to the contractor by registered letter, with the technical officer and technical and IPT group leaders in copy. |
||||
File the letter of notice (both paper and electronic format). |
||||
After the deadline is reached, assess the situation again. Take a decision:
|
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
Ask whether the contract should be extended or not.
|
||||
Confirm whether the contract needs to be extended.
|
||||
Request of formal authorisation of extension to the Finance Committee (FC). |
||||
Prepare the contract amendment in accordance with the contractual notice period. |
||||
Send the signed amendment to the contractor for signature. |
||||
File the contract amendment both in paper and electronic format (using CFU). The original of the amendment is kept by the Procurement service. Both technical and procurement officers shall file the amendment in their own data management system (EDMS for the technical officer). |
Action | Proc. Officer | Tech. Officer | Contractor | |
---|---|---|---|---|
In case of need or request of modification of contract terms (name of the contractor, applicable prices, change of scope etc.), inform the procurement officer in any case.
|
||||
Hold a preparatory meeting as necessary, evaluate the situation based on the conditions defined in the contract:
|
||||
Hold negotiation meetings, as appropriate. |
||||
Prepare the contract amendment (in case a contract change is approved by technical and procurement officers) or correspondence.
|
||||
Send the amendment to the contractor for signature. |
||||
File the contract amendment both in paper and electronic format (using CFU). The original of the amendment is kept by the Procurement service. Both technical and procurement officers shall file the amendment in their own data management system (EDMS for the technical officer). |